P, Q, R and S are working on a project. Q can finish the task in $25$ days, working alone for $12$ hours a day. R can finish the task in $50$ days, working alone for $12$ hours per day. Q worked $12$ hours a day but took sick leave in the beginning for two days. R worked $18$ hours a day on all days. What is the ratio of work done by Q and R after $7$ days from the start of the project?

  1. $10:11$
  2. $11: 10$
  3. $20:21$
  4. $21:20$
recategorized by

Please log in or register to answer this question.

Answer: