$S$, $M$, $E$ and $F$ are working in the shifts in a team to finish a project. $M$ works with twice the efficiency of others but for half as many days as $E$ worked. $S$ amd $M$ have $6$ hour shifts in a day, whereas $E$ and $F$ have $12$ hours shifts. What is the ratio of contribution of $M$ to contribute of $E$ in the project?

  1. $1:1$
  2. $1:2$
  3. $1:4$
  4. $2:1$

7 Answers

0 0 votes

Contribution = efficiency × hours/day × days

M’s work = 2 × 6 × (D/2) = 6D
E’s work = 1 × 12 × D = 12D

Ratio (M : E) = 6D : 12D = 1 : 2

Answer:
Position:
Show:

Related questions

8 8 votes
3 answers 3 answers
625
625 views
Milicevic3306 asked Mar 27, 2018
625 views
The Venn diagram shows the preference of the students population for leisure activities. From the data given, the number of stud...
16 16 votes
2 answers 2 answers
821
821 views
Milicevic3306 asked Mar 27, 2018
821 views
Two and a quarter hours back, when seen in a mirror, the reflection of a wall clock without umber markings seemed to show $1.30$. What is the actual current time shown by...
28 28 votes
1 answers 1 answer
861
861 views
Milicevic3306 asked Mar 27, 2018
861 views
$M$ and $N$ start from the same location. $M$ travels $10$ km east ad then $10$ km North-East. $N$ travels $5$ km South and then $4$ km South-East. What is the shortest d...
13 13 votes
1 answers 1 answer
624
624 views
Milicevic3306 asked Mar 27, 2018
624 views
A wire of length $340$ mm is to be cut into two parts. One of the parts is to be made into a square and the other into a rectangle where sides are in the ratio of $1:2$. ...

Add Synced Question

×