• moved by
1,313 views
16 16 votes

$S$, $M$, $E$ and $F$ are working in the shifts in a team to finish a project. $M$ works with twice the efficiency of others but for half as many days as $E$ worked. $S$ amd $M$ have $6$ hour shifts in a day, whereas $E$ and $F$ have $12$ hours shifts. What is the ratio of contribution of $M$ to contribute of $E$ in the project?

  1. $1:1$
  2. $1:2$
  3. $1:4$
  4. $2:1$

7 Answers

Best answer
26 26 votes
Let the efficiency of $S, E$ and $F$ be $r$ units/hour.
So the efficiency of $M = 2r$ units/hour.

Let the number of days $E$ works be $d$, so that of $M$ is $d/2$.

The amount of work done by $M,$ $W_{m} = 2r \times (d/2) \times 6.$
(As $M$ is working $6$ hours per day)

The amount of work done by $E,$ $W_{e} = r \times d \times 12.$

$W_{m}$ : $W_{e}$ = $\frac{2r \times (d/2) \times 6}{r \times d \times 12} = 1 : 2.$

Correct Answer: $B$
• moved by
6 6 votes
Consider efficiency of M as X , no. of Days E worked as D. $\therefore$ no. of days M worked= $\frac{D}{2}$

$\therefore$ Efficiency of E=$\frac{X}{2}$

$\therefore$ Contribution(M)=X $\times$ $\frac{D}{2}$ $\times$ 6 = 3XD [ $\because$ he has 6 hour shifts ]

$\therefore$ Contribution(E)=$\frac{X}{2}$ $\times$ D $\times$ 12=6XD  [ $\because$ he has 12 hour shifts ]

$\frac{ Contribution(M)}{Contribution(E)}$=$\frac{3XD}{6XD}$=$\frac{1}{2}$
• moved by
1 1 vote
1 1 vote

contribution of a worker =number of days he/she worked$*$number of hours worked per day$*$work done per hour.

Now coming to problem,

Let S,E,F does work of x units/hour.Since M is twice as efficient as others,M does work of 2x units/hour.

Let E works for y days.Then M works for y$/$2 days.

M works for 6 hrs in a day while E works for 12 hrs in a day.

$\therefore$ Contribution of M = (y$/$2)$*$2x$*$6 = 6xy

and Contribution of E = y$*$x$*$12$ = $12xy

Contribution of M$/$Contribution of E $=$1$/$2


The work done can be any thing.It can be eating 2 apples per hour or typing 3 pages per hour...depending on the project.

• moved by
0 0 votes
Option B
• moved by
0 0 votes
Ans. B = 1:2 efficiency.
• moved by
Answer:
Position:
Show:

Related questions

8 8 votes
3 answers 3 answers
684
684 views
Milicevic3306 asked Mar 27, 2018
684 views
The Venn diagram shows the preference of the students population for leisure activities. From the data given, the number of stud...
16 16 votes
2 answers 2 answers
912
912 views
Milicevic3306 asked Mar 27, 2018
912 views
Two and a quarter hours back, when seen in a mirror, the reflection of a wall clock without umber markings seemed to show $1.30$. What is the actual current time shown by...
28 28 votes
1 answers 1 answer
1.0k
1.0k views
Milicevic3306 asked Mar 27, 2018
1,010 views
$M$ and $N$ start from the same location. $M$ travels $10$ km east ad then $10$ km North-East. $N$ travels $5$ km South and then $4$ km South-East. What is the shortest d...
13 13 votes
1 answers 1 answer
679
679 views
Milicevic3306 asked Mar 27, 2018
679 views
A wire of length $340$ mm is to be cut into two parts. One of the parts is to be made into a square and the other into a rectangle where sides are in the ratio of $1:2$. ...

Add Synced Question

×